Structure & Agenda

Project started on the 1st January 2014 and had a duration of five years. The project finished on the 31st December 2018.

The project is composed of five activities, which have the interdependencies as shown in the following graph:

Structure & Agenda graph

A1. Analysis of barriers and specifications of the action

Objetives
The objective is to set the full framework of the current situation, in terms of the needs originating the project from the different points of view of all the stakeholders, and then set an initial analysis of the potential business and exploitation opportunities, legal framework, and general definition of the Pilot to be tested.

Start date: 1 Jan 2014

End date: 31 Dec 2016

A2. Integration of the pilot

Objetives
The aim is to achieve the engineering, assembly and commissioning of the Pilot at the Port of Barcelona. The Pilot consists of three main parts: the LNG ship supply system at port, the NG ship supply system at port, and the “Abel Matutes” ship retrofitting on-board.

Start date: 1 Jan 2014

End date: 1 June 2017

A3. Operation of the pilot and analysis of results

Objetives
This activity will put the Pilot in operation during approximately one year, in order to have a broad range monitorisation of key performance indicators showing results of the operation of the technologies tested in the project.

Start date: 1 June 2017

End date: 31 Dec 2018

A4. Disseminatión, normative harmonisation and replication

Objetives
Having record of the vast knowledge to be gained during the monitoring period of the Pilot, the objective is to achieve an efficient project communication plan, as well as to propose and promote standardisation and regulatory improvements, in order to promote the scaling up of CLEANPORT project to the broadest possible set of other European locations.

Start date: 1 Apr 2015

End date: 31 Dec 2018

A5. Management and coordination of the study

Objetives
The aim of this activity is to plan, organise, motivate, and to control resources, procedures and protocols, in order to achieve the project specific goals. It will also co-ordinate the project teams and entities, including the advisory panels and other EU initiatives.

Start date: 1 Jan 2014

End date: 31 Dec 2018

A6. Communication and dissemination

Objetives
This activity aims at defining and effective communication plan and successfully implementing it throughout the project.

Start date: 1 Oct 2015

End date: 31 Dec 2018